LUSAKA-NDOLA ROAD UPGRADE PROGRESS

The Lusaka-Ndola Road dual carriageway project has made significant progress, with 17.8% completion on the main road and 88.6% completion on the 45km Masangano-Fisenge-Luanshya Road.

The Masangano-Fisenge-Luanshya Road is expected to be completed by December 31, 2024.

Project Overview

Advertisement

The project, launched by President Hakainde Hichilema on May 21, 2024, involves upgrading 327km of the Lusaka-Ndola Road and rehabilitating 45km of the Masangano-Luanshya Road.

The concession agreement, worth US$649,976,167, was signed with MOIC-LN for a 25-year period, including three years of construction and 22 years of operations and maintenance.

Key Features

– Dual Carriageway: Upgrading 327km of the Lusaka-Ndola Road

– Rehabilitation: 45km of the Masangano-Luanshya Road

– Bypasses: 30km long bypasses in Kabwe and Kapiri-Mposhi towns

– Toll Plazas: Two new toll plazas, one on the Masangano-Fisenge-Luanshya Section and another between Chibombo and Kabwe

– Weighbridge: One new weighbridge at Kafulafuta and upgrading the existing one at Kapiri Mposhi

– New Bridge: Construction of a new bridge at Kafubu Bridge in Ndola.